With that in mind, it’s worth a short note to highlight that the alerting in the ez2view ‘Notifications’ widget has flagged that this (postponed) outage commences this morning in the 05:05 dispatch interval (NEM time):
We can see that the outage on Line 17 (i.e. relating to ‘Avon to Macarthur (17) 330kV line and Kemps Creek No.2 or No.3 500/330kV transformer O/S’) is currently expected to be finished by 17:00 (NEM time) on Friday 20th December 2024.
Paul was one of the founders of Global-Roam in February 2000. He is currently the CEO of the company and the principal author of WattClarity. Writing for WattClarity has become a natural extension of his work in understanding the electricity market, enabling him to lead the team in developing better software for clients.
Before co-founding the company, Paul worked as a Mechanical Engineer for the Queensland Electricity Commission in the early 1990s. He also gained international experience in Japan, the United States, Canada, the UK, and Argentina as part of his ES Cornwall Memorial Scholarship.
In the >36 hours since an article on Wednesday the forecasts for LORx on Tuesday 26th November 2024 have become less strident. We start to look at why…
A case study, drawing heavily on various widgets in ez2view, looking at some large (and unexpected) oscillations in output at Darlington Point Solar Farm through a ~2 hour period on Thursday 29th August 2024.
At 10:42 (NEM time) this morning the AEMO published MN124235 pertaining to tomorrow (Friday 7th February 2024) for forecast LOR2 in NSW. So we take a quick look…