The Administered Price Cap has increased to $600/MWh as of today 1st December 2022
A rule change increasing the Administered Price Cap from $300/MWh to $600/MWh, submitted by Alinta Energy, has come into effect today.
A rule change increasing the Administered Price Cap from $300/MWh to $600/MWh, submitted by Alinta Energy, has come into effect today.
QLD looks like it will be without Callide's C3 unit until at least February 2023.
Administered Pricing has ended for FCAS in SA after roughly 12 days.
Yesterday's note from ElectraNet prompted this initial summary of some of what we've seen happen with the SA islanding event over the last 12 days.
A short article, to record the upgrade of the ASEFS and AWEFS forecasts for Semi-Scheduled (i.e. Wind and Large Solar) units.
James Martin from SwitchDin, provides an overview of the state of distributed energy management, and how it relates to last week's events in SA.
On Saturday evening 19th November 2022 the Heywood interconnector returned to service following temporary repairs to the tower damaged on Saturday 12th November.
A short article to record the curtailment of rooftop PV underway in South Australia on Saturday 19th November 2022.
In this article we explore the impacts on wind power generation as the storms passed through, in the leadup to the transmission line trip at 16:39 (NEM time, reflected in the market by the...
Rounding out the working week, there's *currently* no forecast for curtailment of rooftop PV in SA on Friday 18th Nov (but clarifying it did happen on Monday 14th Nov 2022).
In this guest article, Matt Grover from Fluence draws on operational data and real-world trading experience to unpack how Australia’s grid-scale batteries performed across three June 2025 peak days — and what capabilities belong...
With the Queensland state government’s new energy roadmap due out tomorrow, Greg Elkins highlights how distorted signals and state interventions expose a new NEM failure.
N/A