Belatedly noting return to service of VP5 and VP6 after the double-unit trip
On Monday 2nd February 2026 we noted the (almost?) simultaneous trips at Vales Point 5 and Vales Point 6. In this article we belatedly note the return to service.
On Monday 2nd February 2026 we noted the (almost?) simultaneous trips at Vales Point 5 and Vales Point 6. In this article we belatedly note the return to service.
On my commute this morning (Friday 3rd Oct 2025), I noticed this update on LinkedIn yesterday evening from the team at Delta Electricity, speaking about their annual shutdown at Vales Point 5.
A little over 2 weeks ago (on Thu 3rd April 2025) the AEMC made a draft determination on the rule change proposal by Delta Electricity to allow AEMO to accept cash as credit support.
Today the AEMC weekly email notes that: ‘We will use the standard rules consultation process to assess Delta Electricity’s proposal to allow cash as credit support. We received a valid objection to the proposed use of the expedited process, meaning the standard approach will be...
A short note today (thanks to a tip by Thomas MacDonald) about a 'relatively urgent' rule change request by Delta Electricity that might help Vales Point operate into 2025.
On Tuesday morning 21st May 2024 the Vales Point 6 unit has returned to service, ~2 days earlier than earlier expectations.
An early afternoon look (Sat 18th May 2024) about the delays in return to service for the forced outages at two NSW coal units (Eraring unit 2 and Vales Point unit 6).
A quick look at the trip of Vales Point unit 6 on Friday afternoon 17th May 2024.
A brief weekend note about two initiatives commenced by AEMC on Thursday 19th August 2021 - both related to transmission development.