Update to Constraint Violation Penalty (CVP) Factors – effective 19th September 2025
Referencing AEMO's MN129117 published Tuesday 16th September 2025 with respect to this Friday 19th September 2025.
Referencing AEMO's MN129117 published Tuesday 16th September 2025 with respect to this Friday 19th September 2025.
About 4 weeks ago the 2025 ESOO was released. In this article we highlight 3 x 2 different ways this might be viewed - and note some other dimensions not considered.
Also featuring in the (perhaps misnamed) 'Faster than Forecast' session was David Dixon from Rystad - here's two things that jumped out to me.
A short note about some comments made by Oliver Nunn during the 'Faster than Forecast' session at Queensland Clean Energy Summit on Mon 15th Sept 2025.
I thought it was worth noting a couple of observations following the afternoon session at day 1 of Queensland Clean Energy Summit, titled ‘Faster than Forecast’.
Whilst attending day 1 of the CEC’s ‘Queensland Clean Energy Summit 2025’ yesterday we noticed the release of the Climate Risk Assessment, and the Adaptation Plan
A quick article to explore a frequency drop on Thursday evening 11th September 2025.
Worth a short note to point readers here to the current details about the conference – which is to be held in Brisbane on Tuesday 7th and Wednesday 8th October 2025.
Combining together a bundle of different metrics related to the 'availability' of a wind farm, we take a look at what's happened at Bulgana Wind Farm over the past ~25 months.
A short article to look at the first instance of the new ‘V_NWVIC_GFT1_750’ constraint equation binding - on Wednesday evening 10th September 2025 (not 36 hours after it had first been introduced).
We noticed Bruce Mountain’s comments on LinkedIn about Newport power station running overnight, so had a look in ez2view.
A quick note to call attention to this recent alert from NERC with respect to ‘Large Load Interconnection, Study, Commissioning, and Operations’
A brief look at recent operational challenges at Yallourn unit 4.
In this article, we tie together various events since 1st January 2024 that featured either System Frequency outside the NOFB and large AggROT for Semi-Scheduled assets.
Subsequent to earlier article about VP5, the expected duration of the outage pushed out by more than a month.
The AEMO notifies that the new 'V_NWVIC_GFT1_750' constraint equation will first be invoked from 10L00 on Tuesday 9th September 2025.
On Tuesday 26th August 2025 the VP5 unit came offline, with rebid reasons suggesting that ‘turbine vibrations’ were a factor. We take a look ~10 days later.
Today we were alerted that the AEMC had belatedly published this 15-page Staff Working Paper titled ‘Addressing the risk of algorithmic collusion’.
Worth a short note today (Wednesday 3rd September 2025) to record AEMO’s Market Notice 128912 published at 16:10
It was no surprise at all to open the AFR and see 4 different analysts quoted in voicing their concerns about the unrealistic notion that Eraring can close in 2027 ... or perhaps even...