What’s up with Waratah BESS? Is the second transformer back early?

I’ve been out of the office for a couple days and walked back in this afternoon (Friday 10th April 2026) to see that the noted outage profile for the Waratah BESS had changed again.

 

 

What’s in the MT PASA Data?

We see this in the snapshot (at 13:55 NEM time) of the filtered ‘Forecast Convergence’ widget in ez2view, focused to look at the MT PASA DUID Availability data set:

2026-04-10-at-13-55-ez2view-ForecastConvergence-WTAHB1-MTPASA

Keep in mind that:

1)  Readers can click on an image to open a larger resolution one in a different tab;

2)  This widget allows one to ‘look up a vertical’ in order to see ‘that other dimension of time’.

 

As per the annotation:

1)  For the data update AEMO published for 09:00 this morning (so notified to them overnight sometime) the Availability for the unit from this coming Sunday (12th April 2026) is that it will now be available to the tune of 350MW

2)  Readers here should recall:

(a)  how we posted ‘What’s up with Waratah BESS (unplanned outage till 3rd May 2026)?’ on 7th November 2025 after noticing an update to the MT PASA DUID Availability data set for the unit’

… which, it turned out, related to transformer failure onsite on Saturday 18th October 2025.

(b)  how we ‘Belatedly not(ed) that the AER published its PASA Compliance Bulletin and Checklist (back on Friday 29th August 2025)’

(c)  which, it turns out, specified that:

i.  ‘for MT PASA – bid capacity excluding the SIPS reserve capacity, so that this is reflecting the supply condition available to the market more accurately’

ii.  for ST PASA – bid capacity including the SIPS reserve capacity, so this reflects capacity available to AEMO for direction.’

 

So my reading of the above is that either might have happened:

Scenario 1 = it might be that there’s been a development on the transformer front and that there’s more gross capacity available (some still reserved for SIPS, so excluded from the 350MW shown here)

Scenario 2 = or it might be that there’s no new development on the transformer front … but instead that reservation for SIPS until 1st May 2026 is no longer required:

(a)  hence 350MW newly available ‘to the market’

(b)  hence the 350MW bump in the MT PASA DUID Availability data set this morning.

We can’t tell, just from the above, which Scenario it is.

 

What’s in the ST PASA Data?

Given we’re now so close, I wonder whether anything informative is visible in the ST PASA data – so we flip the ‘Forecast Convergence’ widget to look at ST PASA data.  Starting with the ‘Availability’ data, we see the following:

2026-04-10-at-14-20-ez2view-ForecastConvergence-WTAHB1-STPASA-Avail

Quick notes:
1)  The green colour represents the 350MW that’s limited the availability for some months, and the blue represents 700MW

… so that does seem to suggest the second transformer is going to be available a little earlier than expected

2)  The see-saw in the colours on different rows suggests some remaining uncertainty

… perhaps later today, perhaps tomorrow morning, or perhaps later still.

 

Flipping from ‘Availability’ to ‘Max Avail’ we see a much more colourful picture:

2026-04-10-at-14-30-ez2view-ForecastConvergence-WTAHB1-STPASA-MaxAvail

Note that I’ve adjusted the high point in the scale to be 500MW and not 700MW, because the highest number in this grid is only 475MW.

1)  I don’t have time to ponder the ins-and-outs of this…

2)  … other than just to wonder whether this colourful picture shows a lot more of the envisaged operations with respect to a complex SIPS arrangement?

 

 

 

Any news update from Akaysha?

As we hit ‘publish’ here (at 14:43 NEM time Friday 10th April 2026) there’s not yet any news on the Akaysha Energy News section with respect to what appears to be return of the 2nd transformer (i.e. not the 3rd one that failed, but the 2nd one that was taken offline proactively for in-situ testing and repair):

2026-04-10-at-14-26-AkayshaEnergy-News

About the Author

Paul McArdle
Paul was one of the founders of Global-Roam in February 2000. He is currently the CEO of the company and the principal author of WattClarity. Writing for WattClarity has become a natural extension of his work in understanding the electricity market, enabling him to lead the team in developing better software for clients. Before co-founding the company, Paul worked as a Mechanical Engineer for the Queensland Electricity Commission in the early 1990s. He also gained international experience in Japan, the United States, Canada, the UK, and Argentina as part of his ES Cornwall Memorial Scholarship.

Be the first to comment on "What’s up with Waratah BESS? Is the second transformer back early?"

Leave a comment

Your email address will not be published.


*