Why the directions (to 4 units) with 6 coal-fired units still online in Victoria?
We (and others) wondered, why the direction (especially for 4 units) to replace the System Strength from the ‘missing’ coal units?
A collation of articles pertaining to Thursday 14th November 2024.
We (and others) wondered, why the direction (especially for 4 units) to replace the System Strength from the ‘missing’ coal units?
We’ve only just published ‘AEMO directs 4 units on in Victoria, to cover System Strength shortfall’ … noting that, at that time, there were 3 coal units in Victoria offline. Our ‘Notifications’ widget in...
On Thursday morning 14th November 2024, the AEMO has directed 4 different units to operate, to cover a potential system strength shortfall in the Victorian region.