Key network (6C, 6G and 6H) commissioned, as part of capacity release on PEC Stage 2

Given the heightened level of interest in the progressive release of capacity on Project Energy Connect (and some strange initial outcomes) worth another article on Wednesday 4th November 2026 noting MN146032 as follows:

‘——————————————————————-
MARKET NOTICE
——————————————————————-

From : AEMO
To : NEMITWEB1
Creation Date : 04/11/2026 12:37:06

——————————————————————-

Notice ID : 146032
Notice Type ID : GENERAL NOTICE
Notice Type Description : Subjects not covered in specific notices
Issue Date : 04/11/2026
External Reference : GENERAL NOTICE / Network Augmentation Commissioned – NSW Region – 04/11/2026

——————————————————————-

Reason :

AEMO ELECTRICITY MARKET NOTICE
A network augmentation has been commissioned in the NSW Region.
 
At 1230 hrs the following equipment was commissioned:
 
Bunday – Buronga 6C 330 kV Line
Buronga – Dinawan 6G 330 kV Line
Buronga – Dinawan 6H 330 kV Line 
 
This marks the commencement of the South Australia to NSW interconnector testing program, refer to: PEC Stage 2 Internetwork Testing Program.
 
Manager NEM Real Time Operations

——————————————————————-
END OF REPORT
——————————————————————-‘

 


About the Author

Paul McArdle
Paul was one of the founders of Global-Roam in February 2000. He is currently the CEO of the company and the principal author of WattClarity. Writing for WattClarity has become a natural extension of his work in understanding the electricity market, enabling him to lead the team in developing better software for clients. Before co-founding the company, Paul worked as a Mechanical Engineer for the Queensland Electricity Commission in the early 1990s. He also gained international experience in Japan, the United States, Canada, the UK, and Argentina as part of his ES Cornwall Memorial Scholarship.

Be the first to comment on "Key network (6C, 6G and 6H) commissioned, as part of capacity release on PEC Stage 2"

Leave a comment

Your email address will not be published.


*