The shape of PPAs is changing – from volume to value

Australia’s renewable energy market is entering a new phase where the value of electricity is increasingly determined not by energy alone, but by the ability to deliver energy when and where it is needed. ERM argued in early 2025 that the energy transition was overlooking a critical market: the market for risk. Eighteen months after, and the shift from simply paying for renewable output to demanding firmness and shape is already evident. An example deal being the 600MW, 12-year South Australian supply agreement between Firmus and Swiss commodity trading firm Gunvor.

As coal-fired power stations retire, they remove not only physical generation capacity from the National Electricity Market (NEM) but also a significant source of financial hedging products. This will increasingly impact market liquidity of traditional ASX and Over the Counter (OTC) hedging products and drive demand for a new generation of bulk renewable energy, shaping and firming services.

Large renewable energy generators and battery owner-operators can no longer stand on the sideline.

The intersecting policy catalysts, redefining revenue strategies over the next 3-to 5-years

Several intersecting policy initiatives have been driving the transition to a renewable power system in the NEM, with the Federal Capacity Investment Scheme (CIS) taking over from the Commonwealth Renewable Energy Target (RET) Scheme to incentivise pre-2030 investment in renewables and storage alongside the NSW Long-term energy services agreements (LTESA), Victorian Renewable Energy Target (VRET) Scheme and SA Firm Energy Reliability Mechanism (FERM).

Australia’s renewable energy market is now approaching a significant inflection point. Looking beyond 2030, the Electricity Services Entry Mechanism (ESEM) proposed by the NEM Wholesale Market Settings Review Panel, is expected to become a key driver of long-term investment in renewables and storage. Importantly, the ESEM is emerging at the same time as Federal and state government policy initiatives. These policies place obligations on data centres to contract for new renewable supply, as well as address shaping and firmness to contribute towards system reliability.

These policy developments respond to the same underlying market reality: buyers will be seeking solutions that combine energy, shape and firmness. ESEM attempts to create liquid products for these services, while emerging data centre policies seek to mandate their procurement. Together they signal a fundamental shift away from energy-only PPAs.

Unlocking the value premium: why ESEM and data centres are reshaping renewable offtakes

Practical implications of fungibility?

This simply means one MW or MWh is interchangeable with another identical unit, regardless of which project underpins the product. Products must thus be standardised to ensure liquidity. This implies a shift away from the physical project context that has driven many key commercial terms (e.g. force majeure, thermal curtailment, etc.) under run of plant, tolling and capacity swap agreements.

Unlike earlier support schemes, the ESEM is intended to create liquid, standardised products capable of bridging the gap between short-dated exchange-traded contracts and the long-term revenue certainty required to finance large renewable and storage projects. To achieve this, products must be sufficiently fungible and detached from the characteristics of individual projects to support secondary market trading. This represents a fundamental departure from the traditional run-of-plant PPA model.

The legislation and rules required to implement the first tranche of priority ESEM products are expected to be finalised by March 2027. Based on the current design, key implications for renewable generators and storage owners are significant. Rather than transferring shape and volume risk to buyers, sellers will increasingly be expected to manage and underwrite these risks themselves. Capturing the value premium and tenure available under the ESEM will favour asset operators with diversified portfolios, sophisticated trading capability and an ability to manage shape, volume and firmness risk over long contracting horizons.

At the same time, data centres are rapidly emerging as a new category of buyer. The AEMC’s advice to the Commonwealth, the NSW Data Centre Guidelines and Victorian Sustainable Data Centre Action Plan point towards future obligations that require large data centres to support additional renewable generation, firming capacity and demand flexibility. Unlike the corporate PPA buyers that dominated the first wave of renewable procurement, data centres may need integrated solutions that address renewable energy, firming and compliance requirements simultaneously.

For sellers, data centres represent a substantial growth opportunity. However, the capabilities required to compete effectively in this market are likely to mirror those needed under emerging ESEM product constructs, namely the ability to package energy, shaping and firmness solutions through sophisticated portfolio and risk management.

Monitor data centre policy evolution and potential tension at state and federal levels

This is early days in shaping data centre policies, with significant work still to be done to align federal and state policies. To prepare your organisation to be well positioned to capture the data centre opportunity, you must carefully consider both the similarities and differences between the obligations proposed at Federal and state level. Whilst the Victorian energy- related recommendations for data centres suggest alignment with the Commonwealth framework, subject to finalisation, the NSW Government’s proposals differ from the AEMC’s recommendations in several material respects, as outlined below.

Key parameter Common themes AEMC proposal NSW Government proposal
Renewables obligation Transitional period allowing use of certificates backed by existing renewable supply while new generation projects are developed.
  • Potentially less than 100% coverage requirement
  • Technology-neutral approach
  • Proposes Time of Day REGO blocks as a form of partial time matching[1]
  • Existing-generator REGOs permitted during a transitional period tied to project delivery timelines
  • Renewable procurement obligation ramps with data centre load growth, reaching 100% of annual energy demand from new renewable generation by year 4
  • Minimum 40% wind requirement
  • Annual volume matching only (no time-of-day matching)
  • Existing-generator REGOs permitted only for short-term bridging or project delays
  • Minimum 10-year contract term
Firming requirement Diesel backup generation excluded

Seek to ensure new load contributes to system reliability, albeit through fundamentally different mechanisms

  • Dynamic approach linked to evolving system requirements
  • Reliability obligation based on firmness factors assigned to qualifying physical and financial products
  • Compliance potentially reassessed periodically
  • Open-cycle gas turbines explicitly included
  • Static obligation for arrangement term
  • Minimum 4-hour storage capacity equivalent to at least 25% of contracted renewable capacity required
  • Demand flexibility equal to 25% of forecast average load for up to two hour.
  • On-site or proximate storage used for demand flexibility may contribute towards compliance
  • Minimum 10-year contract term
Project eligibility and bankability Frameworks are intended to support investment in new renewable generation and storage.
  • Additionality requirements yet to be finalised
  • Propose to convert REGOs to a compliance instrument, to enhance market signal for investment in new generation
  • Contracts must support projects that have not reached FID at the time of contracting (expansions of existing assets are eligible)
  • Minimum wind requirement designed to improve bankability of wind projects
Implementation mechanism Contemplate a combination of incentives and compliance obligations to influence contracting behaviour. New market participant category to provide visibility of data centre load and establish a regulatory mechanism for renewable and firming obligations Obligations linked to development pathways (e.g. co-location) and planning approval processes to deliver jurisdiction specific outcomes

Looking Ahead: The Next Generation of Offtake Markets

Data centres represent an attractive new class of renewable energy buyer. They have large and growing electricity demand. Furthermore, unlike many energy-intensive industrial sectors, electricity costs, while significant in absolute terms for data centres, often represent a smaller proportion of overall operating costs, which combined with emerging renewable energy and firming obligations may increase both their willingness and ability to pay for renewable energy and firming services.

Whilst significant uncertainty remains around both data centre policy settings and the implementation of NEM Review and ESEM reforms, it is increasingly clear is that the market is moving beyond traditional run-of-plant PPAs. The retirement of coal generation, the emergence of ESEM, and the rapid growth of data centres are accelerating the unbundling of value into three distinct categories:

  • Bulk renewable energy
  • Shaping services
  • Firming services

In this environment, future buyers are likely to seek integrated solutions that combine these elements within a single offtake arrangement. The organisations best positioned to succeed in this next phase of the energy transition are therefore unlikely to be those with the lowest-cost wind, solar or battery assets alone. Instead, competitive advantage will increasingly reside with participants that can offer:

  • Structure products that solve buyer obligations rather than simply sell electricity
  • Effectively monetise shaping and firmness alongside energy, backed by sophisticated trading and risk management capabilities
  • Operate diversified renewable and storage portfolios.

Does your organisation have the trading, portfolio and risk-management capabilities needed to compete in this future market?

 

 

[1] The blocks currently proposed is standard peak, off-peak and shoulder period which in ERM’s assessment does not align with the residual demand shape of a renewables-heavy system the grid now has to manage. Under current AEMC recommendations, buyers risk holding a compliance product that is sub-optimal from a risk management perspective.


About our Guest Authors

Anita Stadler is a Partner and Head of Renewable Energy Investments at ERM.

Anita has more than 30 years of experience in strategic management consulting, banking and renewable electricity contracting. Her current advisory work spans both the buy-side and sell-side of the renewable energy market. Anita led the development of ERM’s (previously Energetics’) corporate power purchase agreement advisory practice, which established a market-leading position in which ERM advised on ~20% of the off-site corporate renewable contracting market in the National Electricity Market between 2020 and 2025, measured by GWh procured by clients. Leveraging her expertise in energy markets, Anita advises renewable electricity asset owners on revenue strategies, incl. structured products, portfolio design and risk management to deliver market leading value propositions. She also supports investors across the renewable energy sector on market entry strategies, transaction due diligence, and investment decision-making, and has advised on numerous mergers and acquisitions.

Gilles Walgenwitz is a Partner and Head of Energy Markets at ERM.

Gilles heads ERM’s specialist team supporting large corporate energy users, renewable generators and storage proponents across Australia’s National Electricity Market. His career spans both technical and commercial disciplines, combining a background in nuclear power plant engineering with financial markets qualifications. He serves as Responsible Manager under ERM’s Australian Financial Services Licence (AFSL #329935), dealing in and providing financial advice on derivatives, with broader responsibility for risk oversight and regulatory governance. Gilles has originated, structured and negotiated a wide range of energy contracts, on the buy side for large manufacturers, miners and technology companies, and on the sell side for renewable energy generators and storage proponents, spanning conventional and renewable PPAs, physical and virtual tolling agreements, and structured products including shaped swaps and hybrid solar-and-storage arrangements. He combines deep quantitative capability, in risk modelling, stress testing and portfolio optimisation, with extensive commercial leadership experience.

Martin Bates is a Consulting Senior Associate at ERM.

Martin specialises in integrating sustainability considerations into energy market strategies, combining strong financial analysis and risk management skills with expertise in energy procurement and market advisory. He has advised on commercial structuring and risk allocation for long-duration energy storage transactions, provides ongoing advisory support for progressive purchasing programs across government and corporate clients, and has contributed to due diligence and market entry strategies for major renewable developers.