Based on ERM’s database of Australian corporate Scope 2 emissions reduction commitments, renewable electricity targets have tended to cluster around milestone years such as 2025, 2030 and 2050. As a result, corporate renewable procurement activity softened through 2025, with many organisations having already secured sufficient supply to meet near-term commitments while viewing 2030 as comfortably distant.
Recent favourable market conditions reinforced this sentiment. Lower wholesale prices, easing futures markets and a growing renewable project pipeline created confidence that procurement opportunities would remain abundant and potentially become more attractive over time.
That assumption is becoming harder to sustain. As 2030 approaches, organisations will need to replace expiring contracts, secure additional renewable supply and close remaining decarbonisation gaps. At the same time, policy reforms, data centre growth, coal retirements and transmission constraints are reshaping market dynamics. Understanding these dynamics, and acting before they fully emerge, may prove to be one of the most important energy procurement decisions many organisations make.
2030: a contracting cliff in the National Electricity Market
The combination of expiring legacy contracts, new corporate demand, retailer re-contracting requirements and the rapid growth of data centres is expected to trigger a significant increase in renewable electricity procurement activity between now and 2030. They account for a cumulative total renewable contracting requirement of approximately 62 TWh per annum by 2030. This reduces to 36 TWh per annum by 2030 if all expiring agreements recontract with their original projects, a still material share equivalent to roughly two-thirds of the NEM’s current annual large commercial and industrial electricity consumption[1].
| ~29 TWh | Electricity retailers’ renewable contracting requirements in the NEM
ERM estimate of the volume of renewable PPAs executed by retailers in the NEM to meet their renewable electricity target (RET) scheme obligations (ending 2030) and not underpinning known corporate renewable PPAs beyond 2030. As existing PPAs roll off, retailers are expected to re-enter the market to secure replacement supply to backfill their customer hedge books. While the regulatory requirement for that replacement supply to be renewable will cease after 2030, retailers are likely to have limited alternatives given the ongoing retirement of thermal generation capacity. Plus, Snowy Hydro’s requirement to source ~9 TWh of renewable power to support the recently announced arrangements for Tomago Aluminium by 2032. Although not included here this demand for renewables will be further amplified by the requirement to replace retiring coal generating capacity. |
|
| ~6 TWh | Existing end user PPAs in the NEM ending between 2027 and end of 2030
The volume of existing Power Purchase Agreements (PPAs) by end users expected to expire by the end of 2030 or earlier. Thus, aligning with the end of the RET as was common practice amongst the first wave of buyers. |
|
| ~15 TWh | New demand from existing large energy users with 2027 to 2030 renewable targets
The demand for renewable electricity from large energy users with 2030 targets (excluding Tomago Aluminium, included in the retailer category). Unlike the first wave of buyers, which was weighted towards lower-energy service-sector organisations, the new generation of buyers are larger, energy-intensive industries. |
|
| ~12 TWh | New data centre load
Renewable electricity demand from new data centres based on emerging government expectations (see section following), and the AEMO’s forecast that data centre consumption will increase three-fold from around 5 TWh currently (9% of NEM large commercial and industrial electricity consumption) to reach ~17 TWh (~21%) by 2030 based on the AEMO 2026 ESOO (Step Change Scenario). The largest increases are in New South Wales (NSW) and Victoria. |
Policy response to the AI revolution is creating a new class of energy buyer
If renewable energy and firming obligations for data centres proceed broadly as proposed, data centres will become the first class of large energy users required to demonstrate both 100% renewable electricity procurement and compliance with prescribed firming requirements.
While uncertainty remains around the final design, the direction of travel is clear: future large-scale data centres will need to secure renewable energy and dispatchable capacity, either directly or through intermediaries. Given the scale of planned developments and the historical procurement preferences of hyperscale and major colocation providers, direct contracting with renewable generation and storage assets is likely to be common.
Data centres contracting directly with renewable and storage asset owners should not treat renewable energy and firming obligations as separate from their broader electricity procurement strategy. Even portfolios that achieve a high degree of renewable matching can remain exposed to significant basis risk, as renewable generation and storage contracts typically settle against spot market prices while retail electricity supply agreements are often linked to futures market prices. This disconnect between spot-settled generation revenues and futures-linked electricity costs can become one of the most material sources of portfolio risk. It can be mitigated through a managed spot-exposed supply strategy or by integrating renewable generation, storage and wholesale hedging products into a “sleeved” retail supply arrangement.
Accordingly, organisations should not wait for final policy settings to be known before acting. The immediate priority should be to define a target operating portfolio and establish a robust risk framework before engaging the market. When engaging the market, the ultimate objective in our view is not to maximise volumetric matching at every interval. Rather, it is to construct a portfolio that minimises residual net cost exposure across a range of market conditions while remaining within the organisation’s risk tolerance threshold.
That work should begin now. Those that wait may find the most attractive renewable, storage and shaping opportunities have already been secured. As the market evolves, buyers should also evaluate emerging contract structures alongside traditional PPAs, capacity swaps and virtual tolls, as new products may offer more efficient ways to manage risk and capture value in a high-renewables electricity system.
Is there sufficient supply to meet the growing demand for renewables and storage?
Australia’s renewable and storage development pipeline appears strong on paper. The 2026 ESOO forecasts no NEM-wide reliability gap before 2030-31, but that outlook assumes the successful delivery of around 50 GW of committed and anticipated generation and storage projects.
The challenge is that only around 21% of this capacity is fully committed, with the balance still subject to varying degrees of financing, contracting, transmission and delivery risks. When AEMO models a scenario including committed projects only, reliability shortfalls emerge in NSW, Victoria and Queensland from as early as 2029-30, well within today’s ASX contracting horizon.
Many anticipated projects continue to face execution challenges, including cost escalation, financing hurdles, grid connection delays and dependence on major transmission projects:
- Of the 31 wind projects awarded support under the federal CIS, only three have reached financial close in the NEM, with construction costs increasing 30-50% since bids were submitted.
- Across the broader CIS pipeline, only 1.9 GW of 10.4 GW of anticipated projects have reached financial close, representing an 18% conversion rate over two years.
- AEMO’s June 2026 Connections Scorecard shows project progression is slowing, with 25% of projects spending more than 30 months in the “Proponent Implementation” phase, roughly double the duration observed three years ago.
- Policy and transmission uncertainty also remain material risks. For example, recent proposals to halt or review VNI-West and the Western Renewables Link could affect the viability of more than 11 GW of early-stage renewable projects across Victoria and NSW (i.e. 8.5 GW in Victoria, or 1.15x current installed renewable capacity in the state, and a further 3.2 GW in NSW).
For buyers, the key takeaway is simple: the size of the development pipeline is less important than the volume of projects that can realistically be financed, constructed and connected on schedule. A large pipeline should not be mistaken for an abundance of readily available procurement opportunities. As demand for renewable energy and storage accelerates, competition for bankable projects is likely to intensify.
Adequacy of renewable generation capacity?
Note ERM’s definitions differ from AEMO’s
ERM defines in the chart below:
- Committed: refers to projects that are under construction, have reached FID or have secured an offtake with an end-user or wholesale market participant.
- Anticipated: refers to projects that have received development approval, a connection agreement with their respective network service provider or a government underwriting agreement.
- Early-stage: refers to projects that have applied for a connection agreement or development approval.
The chart below presents our assessment of the adequacy of supply in NSW in the period to 2032, noting corporate decarbonisation commitments, including Tomago Aluminium’s 100% renewable target by 2033; and NSW Government proposed policy that permit the use of offtake from operational projects until year four of a data centres operation.

Figure 1: Forecast electricity supply adequacy in NSW relative to forecast corporate renewable demand by 2032
The analysis indicates that forecast renewable demand from end users with pre-2032 renewable targets that have not yet contracted (new anticipated demand above) and new data centres (~15 TWh) absorb ~40% of the entire committed and anticipated pipeline in NSW (~36 TWh) over the period to 2032.
Add to that the volume for corporates re-contracting for renewables and Tomago’s requirements, then ~80% of the committed and anticipated pipeline would be required. When considering the volumes required to replace Eraring power station scheduled to retire in 2029 (~15TWh), early-stage projects would be required to come on-line to close this gap, before considering the volumes required to replace Bayswater and Mt Piper power stations in NSW (expiring in 2033).
Taken together, these factors point to an increasingly competitive market for renewable offtakes through to 2032. Given the inherent risk of development delays among anticipated projects and the likelihood that many early-stage projects will not proceed to construction, access to high-quality renewable supply is expected to become progressively more constrained over time. Importantly, this outlook assumes no material increase in underlying corporate demand beyond commitments already identified.
Adequacy of storage capacity?
In contrast to renewable generation, the NSW storage pipeline appears materially deeper relative to forecast firming demand, although future demand for firming services outside the data centre sector is inherently more difficult to quantify. Key assumptions include:
- Data centres are assumed to require firming capacity equivalent to 25% of contracted renewable generation capacity (MW), consistent with currently proposed NSW policy settings.
- The same 25% firming requirement has been applied to forecast industrial renewable procurement, including Tomago Aluminium, as a simplifying assumption.
- Merchant traders, commodity trading houses and other non-load-serving participants have not been explicitly modelled, despite their growing role in providing shaping, balancing and firming services. Demand from this segment may further increase in response to increased volatility in response to events such as coal exiting, or further delays in Snowy Hydro 2.0 commissioning.
While the storage development pipeline is substantial, a significant proportion remains at an early stage of development. At the same time, declining spot market volatility and narrowing arbitrage opportunities across NSW and the broader NEM are reducing the attractiveness of merchant battery investment. As a result, a meaningful share of the early-stage battery pipeline will not proceed without contracted revenue support.
Table 1: Forecast firming demand in NSW relative to storage project pipeline by 2032[2]
| Supply | Volume (MW) |
| Committed (Pre-FID) storage | 1,100 |
| Anticipated storage | 11,100 |
| Early-stage storage | 21,800 |
| Total | 34,000 |
| Demand | |
| Residual retailer demand | 300 |
| DC firming requirements | 2,400 |
| Industrial firming (incl Tomago) | 3,600 |
| Total | 6,300 |
| Net position by 2032 | >26,000 |
This dynamic is likely to increase competition among developers seeking long-term firming offtake agreements, potentially improving contracting outcomes for large energy users and data centres. As shown in Table 1, the committed and anticipated storage capacity in NSW appears more than sufficient to accommodate expected firming requirements through to 2032.
However, this apparent surplus should be interpreted cautiously. The estimated residual retailer firming demand assumes all projects in major NSW retailers’ development pipelines (including early-stage and announced projects) progress on schedule and are used to support customer load.
Furthermore, whilst the retirement of Eraring power station is considered in the residual retailer demand calculation, this analysis excludes the substantial firming requirement that will emerge as NSW coal-fired power generation capacity retires beyond 2033. In practice, contracting activity to replace these assets is likely to commence well before their closure dates, creating additional demand for storage and flexible capacity during the period to 2032. The scale of the challenge is depicted in the 2026 ESOO, which forecasts a 70x increase in the magnitude of unserved energy in NSW in 2034 following the exit of Bayswater and Mount Piper power stations based on AEMO’s “Committed and Anticipated Developments” forecast.
Conclusion: Renewable procurement is a strategic risk management exercise
Australia remains less than halfway through its energy transition, and the next five years are likely to see increasing competition for renewable generation, storage and firming capacity. Growing demand from corporates, retailers and emerging energy-intensive sectors such as data centres is expected to coincide with ongoing uncertainty around the delivery of generation, storage and transmission infrastructure.
For large electricity users, the challenge is no longer simply securing renewable energy volumes. Success will increasingly depend on developing a clear target portfolio, understanding risk exposures, and evaluating a broader range of contracting structures beyond traditional PPAs. Procurement decisions should be assessed through a long-term portfolio optimisation and risk management lens, rather than renewable volume matching alone.
Organisations that engage early, establish a robust risk framework and remain open to emerging contracting solutions are likely to be best positioned to capture value. Those that assume current market conditions will persist, or treat renewable procurement primarily as a compliance exercise, may face fewer options and less favourable outcomes as competition intensifies toward 2030.
[1] Annual NEM consumption with Residential and Business Mass Market components removed, AEMO 2026 ESOO.
[2] AEMO 2026 ESOO data is used to inform growth in retailer customer load in NSW (equivalent to P10 max demand forecast) and data-centre demand growth rates, Step Change scenario.
About our Guest Authors
|
|
Anita Stadler is a Partner and Head of Renewable Energy Investments at ERM.
Anita has more than 30 years of experience in strategic management consulting, banking and renewable electricity contracting. Her current advisory work spans both the buy-side and sell-side of the renewable energy market. Anita led the development of ERM’s (previously Energetics’) corporate power purchase agreement advisory practice, which established a market-leading position in which ERM advised on ~20% of the off-site corporate renewable contracting market in the National Electricity Market between 2020 and 2025, measured by GWh procured by clients. Leveraging her expertise in energy markets, Anita advises renewable electricity asset owners on revenue strategies, incl. structured products, portfolio design and risk management to deliver market leading value propositions. She also supports investors across the renewable energy sector on market entry strategies, transaction due diligence, and investment decision-making, and has advised on numerous mergers and acquisitions. |
|
|
Gilles Walgenwitz is a Partner and Head of Energy Markets at ERM.
Gilles heads ERM’s specialist team supporting large corporate energy users, renewable generators and storage proponents across Australia’s National Electricity Market. His career spans both technical and commercial disciplines, combining a background in nuclear power plant engineering with financial markets qualifications. He serves as Responsible Manager under ERM’s Australian Financial Services Licence (AFSL #329935), dealing in and providing financial advice on derivatives, with broader responsibility for risk oversight and regulatory governance. Gilles has originated, structured and negotiated a wide range of energy contracts, on the buy side for large manufacturers, miners and technology companies, and on the sell side for renewable energy generators and storage proponents, spanning conventional and renewable PPAs, physical and virtual tolling agreements, and structured products including shaped swaps and hybrid solar-and-storage arrangements. He combines deep quantitative capability, in risk modelling, stress testing and portfolio optimisation, with extensive commercial leadership experience. |
|
|
Lachlan Goodland-Smith is a Senior Consultant at ERM.
He is a specialist in NEM market forecasting and commercial analysis, leading the modelling for large-scale renewable PPA procurement programs and conducting energy options assessments to support cost-effective renewable energy transactions. He has also advised on portfolio hedging and firming strategies and supported commercial due diligence of renewable and battery storage portfolios for developers and infrastructure investors. Lachlan leads the development of ERM’s monthly client market report, which includes original research into pertinent aspects of the energy system, and is responsible for the ongoing development of ERM’s proprietary corporate PPA deal tracker, a leading reference for the renewables industry and corporates in Australia. |