More delays in the commissioning process for the Hunter GT (a.k.a Kurri Kurri)

Frequent readers will recall that we’ve posted a number of articles collated here in relation to the Kurri Kurri Gas-Fired Generator, which has been a long time coming as a project.

Several of our readers have been taking a keen interest in this project, and periodically providing prompts to us about things they have seen in the AEMO data and elsewhere

… and on Monday 8th June 2026, Angela MacDonald-Smith wrote ‘Snowy, UGL argue over cost blowout at $1.3b-plus NSW gas power plant’ in the AFR.  That article contained the interesting observations that:

‘Snowy Hydro is in no rush to bring its new Kurri Kurri gas power station fully online, as it focuses on negotiations with principal contractor UGL over who should pay for cost blowouts and delays at a generator currently not needed by the market.’

 

That’s prompted me to open up the ‘Forecast Convergence’ widget in ez2view and look at a 3 year + 3 year view of the MT PASA DUID Availability data set for the ‘HUNTER’ Station as follows:

2026-06-08-at-18-35-ez2view-ForecastConvergence-HUNTER-MTPASA-Avail

Remember that this widget allows one to ‘look up a vertical’ in order to see ‘that other dimension of time’.

In the snapshot above, we see a large number of discrete delays to the expected availability profile since it first appeared in the AEMO data (WHEN).

If we zoom into the top of the display, we can see the latest delay … meaning that the first instance of non-zero availability is not until the 30th June 2026 (though, given the comments noted above in the AFR, one would have to view even that date as rubbery):

2026-06-08-at-18-40-ez2view-ForecastConvergence-HUNTER-MTPASA-Avail-ZoomedIn

 

 

Also thought it was worth adding this snapshot from the ‘Bids & Offers’ widget in ez2view to highlight that:

1)  The plant did get a run through May:

(a)  On Thursday 14th May 2026; and

(b)  On Monday 25th May 2026, and on Tuesday 26th May 2026.

… which I’d written about with ‘Both units at Hunter GT get a test run’.

2)  But note:

(a)  Have not run since that time (not even any plant-related rebids since 26th May 2026); and

(b)  Availability for Unit 1 (which was noted as being from Monday afternoon 1st June 2026) was obviously pushed back…

 

2026-06-08-at-19-05-ez2view-BidsOffers-HUNTER

Also worth noting that the ‘PASA Avail’ for the station is being bid at full load … which some might read to infer that the unit would be available (subject to a notice period) should AEMO require it to run

…. and so back to the comments noted by Angela above about the market not needing it, at present.


About the Author

Paul McArdle
Paul was one of the founders of Global-Roam in February 2000. He is currently the CEO of the company and the principal author of WattClarity. Writing for WattClarity has become a natural extension of his work in understanding the electricity market, enabling him to lead the team in developing better software for clients. Before co-founding the company, Paul worked as a Mechanical Engineer for the Queensland Electricity Commission in the early 1990s. He also gained international experience in Japan, the United States, Canada, the UK, and Argentina as part of his ES Cornwall Memorial Scholarship.

Be the first to comment on "More delays in the commissioning process for the Hunter GT (a.k.a Kurri Kurri)"

Leave a comment

Your email address will not be published.


*