Given the earlier articles about Thursday 1st January 2026, worth a short note with a NEMwatch snapshot at 13:35 NEM time, marking the lowest points reached for ‘Market Demand’ in both VIC and SA today:
In both those regions, and on a NEM-wide basis, the ‘Market Demand’ has begun to climb slowly into the afternoon … so these low points might be the lowest seen today (and still a margin above the all-time minimums)
Highlighted on the image are the two Market Notices speaking about ‘Minimum System Load’ alerts for both regions:
| MN 132356
speaking to ‘actual MSL2’ in South Australia |
MN 132355
speaking to ‘actual MSL1’ in Victoria |
|---|---|
| ——————————————————————- MARKET NOTICE ——————————————————————- From : AEMO ——————————————————————- Notice ID : 132356 ——————————————————————- Reason : AEMO ELECTRICITY MARKET NOTICE AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the SA on 01/01/2026. Minimum demand is forecast to be -230 MW at 1330 hrs, and the advisory threshold is: The demand is below the MSL2 threshold. The actual MSL2 condition is forecast to exist until 1400 hrs. Forecast demand refers to forecast Operational Demand that excludes contribution from Significant Non-Scheduled Generation: see definitions at https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/operational-demand-data . Manager NEM Real Time Operations ——————————————————————- |
——————————————————————- MARKET NOTICE ——————————————————————- From : AEMO ——————————————————————- Notice ID : 132355 ——————————————————————- Reason : AEMO ELECTRICITY MARKET NOTICE Update to Market Notice 132340 – AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 01/01/2026. Minimum demand is forecast to be 1620 MW at 1130 hrs, and the advisory threshold is: The demand is below the MSL1 threshold. The actual MSL1 condition is forecast to exist until 1530 hrs. Forecast demand refers to forecast Operational Demand that excludes contribution from Significant Non-Scheduled Generation: see definitions at https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/operational-demand-data . Manager NEM Real Time Operations ——————————————————————- |