Worth a short note with this snapshot from the ‘Bids & Offers’ widget in ez2view to highlight that Bayswater unit 2 is in the process of returning to service on Friday morning 19th December 2025:
Paul was one of the founders of Global-Roam in February 2000. He is currently the CEO of the company and the principal author of WattClarity. Writing for WattClarity has become a natural extension of his work in understanding the electricity market, enabling him to lead the team in developing better software for clients.
Before co-founding the company, Paul worked as a Mechanical Engineer for the Queensland Electricity Commission in the early 1990s. He also gained international experience in Japan, the United States, Canada, the UK, and Argentina as part of his ES Cornwall Memorial Scholarship.
References to WattClarity in today’s session of the Senate Committee on Energy Planning and Regulation in Australia (between Matt Canavan and Daniel Westerman) spiked our interest – and, given the topic was NSW unit outages on Wednesday 27th November 2024, we took a quick look.
AGL released its investor presentation yesterday – several people flagged the availability stats within the presentation (they knew we were looking at aspects of reliability for our Generator Report Card 2018). Hence I take a brief detour and have a quick look.
I was keen to see if there was any noticeable blip in System Frequency resulting from the BW02 unit coming offline on Saturday 4th October 2025 for the brief (two-shift) outage.