So (just looking at the MT PASA DUID Availability data, and not going further to look at the newer and more granular PD/ST PASA data) this all seems to tie together…
Paul was one of the founders of Global-Roam in February 2000. He is currently the CEO of the company and the principal author of WattClarity. Writing for WattClarity has become a natural extension of his work in understanding the electricity market, enabling him to lead the team in developing better software for clients.
Before co-founding the company, Paul worked as a Mechanical Engineer for the Queensland Electricity Commission in the early 1990s. He also gained international experience in Japan, the United States, Canada, the UK, and Argentina as part of his ES Cornwall Memorial Scholarship.
We noticed today (Wednesday 24th September) an ~8 week extension added onto the expected return to service date for YWPS2, which tripped offline due to ‘LP turbine issues’ in August 2025.
Given the tight supply-demand balance forecast for NSW and QLD this week, it’s worth revisiting the ‘Generator Outages’ widget in ez2view at 15:35 on Sunday 24th November 2024 to show what the current status is of generator outage plans