Yesterday afternoon we noted that ‘ER03 now (again) slated to come offline early Thursday morning 25th September 2025’ … and that, at least in part as a result, the ‘AEMO notes possible early-morning direction in NSW on Thursday 25th September 2025’.
As a short follow-on article now mid-morning Thursday 25th September 2025 it’s worth including this updated snapshot of the ‘Forecast Convergence’ widget in ez2view at the 10;10 dispatch interval (NEM time) as follows:
With this widget:
1) Remember that the ‘Grid’ view in ‘Forecast Convergence’ allows one to ‘look up a vertical’ in order to see ‘that other dimension of time’;
2) With the widget now having more functionality to delve into unit availability* in the new PD/ST PASA timeframe, due to the new PDPASA/STPASA data published by AEMO from 31st July 2025
* even for Semi-Scheduled assets
(a) hurrah (at least in PD/ST PASA),
(b) albeit not yet in MT PASA DUID Availability!
3) We see that the key change was made prior to the 20:00 data update from the AEMO, to push back the start date of the outage at ER03 until the early hours of Saturday morning 27th September 2025 .
This will have been a key driver in AEMO’s then issuing MN129282 at 20:09 yesterday as follows:
‘——————————————————————-
MARKET NOTICE
——————————————————————-
From : AEMO
To : NEMITWEB1
Creation Date : 24/09/2025 20:09:16
——————————————————————-
Notice ID : 129282
Notice Type ID : MARKET INTERVENTION
Notice Type Description : Reserve Contract / Direction / Instruction
Issue Date : 24/09/2025
External Reference : Cancellation – Foreseeable intervention to manage system strength in NSW region 24/09/2025
——————————————————————-
Reason :
AEMO ELECTRICITY MARKET NOTICE
Cancellation – Foreseeable intervention to manage system strength in NSW region 24/09/2025
Refer Market Notice 129279
AEMO no longer foresees a possible requirement for intervention to manage system strength in NSW region. The advice of possible intervention is cancelled from 2000 hrs 24/09/2025.
Manager NEM Real Time Operations
——————————————————————-
END OF REPORT
——————————————————————-’
… and then also MN129283 at 20:48 as follows:
‘——————————————————————-
MARKET NOTICE
——————————————————————-
From : AEMO
To : NEMITWEB1
Creation Date : 24/09/2025 20:48:52
——————————————————————-
Notice ID : 129283
Notice Type ID : RESERVE NOTICE
Notice Type Description : LRC/LOR1/LOR2/LOR3
Issue Date : 24/09/2025
External Reference : PDPASA – Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/09/2025
——————————————————————-
Reason :
AEMO ELECTRICITY MARKET NOTICE
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 129277 is cancelled at 2030 hrs 24/09/2025.
Manager NEM Real Time Operations
——————————————————————-
END OF REPORT
——————————————————————-’
That’s all for now…