In the first article we used aggregate data for ST PASA to speculate that Eraring might be offline until Tuesday 21st May 2024 … well, the MT PASA DUID Availability data has updated now in the ‘Generator Outages’ widget in ez2view to confirm that hypothesis:
So with Eraring unit 2 it’s a ‘watch this space’.
In better news, also highlighted shows that Millmerran unit 1 has just started coming back online this morning, slightly earlier than prior expectations after its Planned Outage.
Paul was one of the founders of Global-Roam in February 2000. He is currently the CEO of the company and the principal author of WattClarity. Writing for WattClarity has become a natural extension of his work in understanding the electricity market, enabling him to lead the team in developing better software for clients.
Before co-founding the company, Paul worked as a Mechanical Engineer for the Queensland Electricity Commission in the early 1990s. He also gained international experience in Japan, the United States, Canada, the UK, and Argentina as part of his ES Cornwall Memorial Scholarship.
An early afternoon look (Sat 18th May 2024) about the delays in return to service for the forced outages at two NSW coal units (Eraring unit 2 and Vales Point unit 6).
Friday 14th July 2023 sees some media articles and commentary about several coal-fired generators running longer than previously thought, as the energy transition hits some speed bumps.
Be the first to commenton "MT PASA DUID Availability confirms Eraring unit 2 offline till Tuesday 21st May 2024"
Be the first to comment on "MT PASA DUID Availability confirms Eraring unit 2 offline till Tuesday 21st May 2024"