The early wind farms reaching 20 years: how are they performing?

Over my Christmas break, I came across a nostalgic LinkedIn post from former Pacific Hydro CEO, Rob Grant, who reminisced over the 20th anniversary of the commissioning of Challicum Hills Wind Farm in Victoria.

 

As Rob notes, the wind farm achieved many firsts for utility-scale wind generation in Australia. Similarly, I’ve also seen Fleur Yaxley, who was the project manager, retroactively dub it as the project that launched an industry.

Although Challicum Hills was given a 25-year life expectancy, the current CEO of Pacific Blue (formerly known as Pacific Hydro) Domenic Capomolla states that he is optimistic that the generator can extend its lifespan beyond 2030. This statement, along with further social media comments wondering about the potential LCOE for the project has peaked my interest to loop back to some analysis I published in early November. In that short piece, I pondered the curtailment and site scarcity effects across wind farms by the year they were first connected to the NEM.

Here I’m going to focus in on the long-term technical and commercial performance of the NEM’s first batch of utility-scale wind farms. In this case study I’ve selected the seven units in the table below as 1) there was sufficient data on each project;  and 2) they are all likely to be in, or approaching, the final 5 years of their expected design life.

 

Table 1: Seven of the oldest utility-scale wind farms in the NEM

Wind Farm

(DUID)

Region Max Capacity Approx. Construction Completed Original Expected Lifespan Reported Construction Cost

(AUD$ at the time *) 

Challicum Hills Wind Farm 

(CHALLHWF)

VIC 52 MW August 2003

Source

25 years

Source

$76m

Source

Starfish Hill Wind Farm

(STARHLWF)

SA 35 MW July 2003

Source

25 years

Source

$65m

Source

Woolnorth Wind Farm

(WOOLNTH1)**

TAS 140 MW Bluff Point –  August 2004

Studland Bay – June 2007

Source

N/A $172.5m

$80m Bluff Point & $92.5m Studland Bay

Source

Lake Bonney Stage 1 Wind Farm

(LKBONNY1)***

SA 81 MW June 2005

Source

25 years

Source

$236m

$700m for Stage 1, 2, and 3 combined

Source 1 and Source 2

Wattle Point Wind Farm

 (WPWF)

SA 91 MW May 2005

Source

25 years

Source

$180m

Source

Mt Millar Wind Farm

(MTMILLAR)

SA 70 MW December 2005

Source

N/A $130m

Source

Cathedral Rocks Wind Farm 

(CATHROCK)

SA 66 MW February 2007

Source

20 years +

Source

$160m

Source 1 and Source 2

Notes with respect to the above:

*  Reported construction costs are assumed to be reported in AUD$, and are not adjusted for inflation at this point.

**   WOOLNTH1 unit consists of two sites (Bluff Point and Studland Bay) completed in stages between 2004 and 2007. The TAS region was not connected to the NEM until 2005 upon the completion of Basslink.

***  LKBONNY1 is one unit, and is not to be confused with Stage 2 and 3 of the project which were developed later between 2006 and 2010. Construction costs for Stage 1 are an estimation based on a capacity split of combined project costs.

Technical Performance

In my November article titled ‘Bigger or better: Are newer wind farms outperforming older ones?’ I looked at capacity factor for all wind farms, new and old, across the NEM.  Capacity Factor as a metric relates most closely to revenue and market value. That article was well received – but a number of readers suggested that (because of increasing curtailment for network and economic reasons) that availability factor would be a more robust measure of technical performance for wind farms as it better encapsulates available wind conditions on site.

For this analysis, however, we can’t use Availability Factor, as these seven wind farms have spent the vast majority of their lifetimes thus far as Non-Scheduled units, which:

  • Do not participate in the central dispatch process;
  • So do not publish any availability data.

As Paul noted here recently, because of the increasing challenges of declining demand in the NEM, particularly the SA Region, several Non-Scheduled wind farms have begun operating as Semi-Scheduled units more recently. At this point, this has happened in two tranches:

  1. On 9th December 2021, some Non-Scheduled Wind Farms (e.g. Lake Bonney 1 and Wattle Point) started operating like Semi-Scheduled units.
  2. On 1st February 2022, three others (e.g. Cathedral Rocks, Mt Millar and Starfish Hill) also changed their mode of operations.

It’s only from the time of those transitions that we have access to Availability for each dispatch interval, so could calculate availability factor – which is not enough history for the purpose of this article.

For this reason, in the chart below I have trended monthly capacity factors for each of these wind farms. For context, I have also plotted the timeline of their schedule status along with the 12-month rolling average of their monthly capacity factor.

Chart 1: Monthly capacity factors (bars) and 12-month rolling average (lines) for these seven units.

Source: Generator Statistical Digest

Note: Although these wind farms may have been connected earlier, publicly available market data only exists from January 2006 onwards.

The graphic above is fairly data-rich, so, for ease of viewing, readers can view a higher-resolution version here.

To examine and compare the long-term trends of each of these wind farms against one another I have extracted the 12-month rolling average figures and re-scaled the y-axis into the new chart below.

Chart 2: Long-term 12-month rolling capacity factors for each of these seven units.

Source: NEMreview

Note: Since start of available data in January 2006. Not adjusted for inflation.

I’ve highlighted Woolnorth (Green), Cathedral Rock (Orange), and Lake Bonney 1 (Yellow) as they show a pronounced slow but declining trend over the past four years. Also, a more recent declining trend for Challicum Hills (Faded Blue), Starfish Hill (Faded Red), Wattle Point (Faded Purple), and Mt Millar (Faded Brown) over the past two years. Declines over the past two years might be somewhat attributed to the change of schedule type (for those based in SA) as mentioned above. Marcelle Gannon, has previously examined the early changes in operations/behaviour of these units since the change.

In addition to this, I will also note that all of these wind farms would have originally signed long-term ‘old style’ PPAs that did not have any contractual obligation to avoid negative prices – which have been accelerating in frequency. Some of these contracts may have expired or been re-negotiated in more recent years – although this would be commercial-in-confidence in any case.

Commercial Performance

As stated, it is expected that these seven wind farms would have been fully or almost-fully hedged under a relatively straightforward pass-through PPA for most of their existence. These wind farms will also have earned revenues for their LGCs as well – as we regularly cover in our GenInsights Quarterly Updates.

As such, ‘black’ spot revenue returns will likely not directly reflect the actual revenues earned by the owners and operators of these generators. However, there is always some counterparty that is exposed to spot prices – so calculating spot revenue on a long-term basis does provide insight into the relative market value of these projects over their lifetime.

In this first chart, we’ve simply trended the cumulative ‘black’ spot revenue earned by these projects over time and I will note:

  • The somewhat different start points for the assets (albeit that these revenues are only calculated starting in January 2006); and
  • More importantly, the different sizes of the assets.

 

Chart 3: Cumulative ‘black’ spot revenue for each of these seven units since January 2006 (start of available data).

Source: NEMreview

Note: Since start of available data in January 2006. Not adjusted for inflation.

To put these cumulative numbers in futher context, in Chart 4 below I have normalised these numbers against the reported construction costs and the capacity of each of those units.

 

Chart 4: The reported construction costs minus the cumulative ‘black’ spot revenue, per megawatt of capacity, for each of these seven units.

Note: Since start of available data in January 2006. Not adjusted for inflation.

Source: Generator Statistical Digest

Hopefully, this chart adds some colour to discussions about the market viability of these projects with the benefit of hindsight. But I would warn readers against drawing their own conclusions about a ‘return on investment’ as there is much deeper to dive (e.g. hedging positions, cost of debt, maintenance costs, FCAS costs, amounts received from any grants, LGC revenue,  etc. etc.) – and this is almost impossible to estimate reliably from the outside, as much of this information is commercial-in-confidence.

Further Reading

The data used in this analysis has been sourced from our Generator Statistical Digest (GSD) data extract from successive years.

For each generating unit in the NEM, the GSD provides detailed operational and financial performance statistics such as spot and FCAS revenue, bid volumes, marginal loss factors, price harvest, capacity factor range, etc. The image below shows the profile of Macarthur Wind Farm taken from last year’s edition.

The next edition of our GSD (the GSD2023) is scheduled to be released early next month. We are progressively compiling more information about the GSD2023 here – and will, when it is released, also feature a number of pieces of analysis from different analysts focused on different aspects of the expanded GSD2023, similar to what we did for the release of the GSD2022 on 31st January 2022.

You can pre-order your copy today using this form.


About the Author

Dan Lee
Dan Lee first started at Global-Roam in June 2013. He has departed (and returned) for a couple of stints overseas in that time, but rejoined our team permanently in late 2019. More recently, Dan's focus has been on growing his understanding of the market and developing his analytical capabilities. He is currently enrolled in the Master of Sustainable Energy program at the University of Queensland.

4 Comments on "The early wind farms reaching 20 years: how are they performing?"

  1. Dan
    Great article very interesting.
    Looks like most will exceed their design life but the fall from ~28% to ~20% in CF may accelerate their replacement with larger turbines. Their break even time is longer than I expected and curtailment will probably increase. It would be interesting to see a similar analysis on Solar..

  2. Understand the unscheduled 12 MW Windy Hill Wind Farm in Far North Queensland was not selected for your excellent article. However, it could be the trail blazer for what happens when a wind farm is decommissioned as it was commissioned in 2000, three years earlier than the oldest WF in this article.

    Also as far as I’m aware there isn’t a wind turbine fire database. Think this should be mandatory as any fire caused by a wind turbine could have have catastrophic impacts, especially if the wind farm is on forested ridge difficult for firefighters to fight. It may also give investors some insight as to what turbines are best suited to the Australian climate.

  3. Realise your list is curated but would have been interesting to see analysis of the Toora Wind Farm – it predates most of these by at least a year, though is smaller (21MW).

  4. The original Albany Wind Farm (Western Australia) was commissioned in October 2001, after ten years of planning. The wind farm has the capacity to produce 80 per cent of the electricity requirements of Albany. Originally commissioned in 2001 the farm was the largest of its kind in Australia.
    courtesy of wikipedia